SECTION 3.0: INSTALLATION, REMOVAL AND ADJUSTMENT
WARNING
Insertion ow meters may be installed in pipes which are under high pressure. Accidents with
these systems can cause serious injury or death. Only persons experienced with high pressure
systems and related knowledge in the heating, cooling and uid metering elds should attempt
to install, adjust, or remove the ow meter. Please read all instructions before attempting to
insert or remove a ow meter.
!
ONICON will be happy to assist with technical recommendations and to provide guidance by
telephone or e-mail. On-site eld engineering, installation and service is also available at additional cost.
3.1 INSTALLATION SITE SELECTION
Install the ow meter where it will be accessible for personnel to perform necessary periodic
maintenance. The clearance required for installation is typically 30”- 40” from the pipe wall to
the nearest obstruction above the valve assembly. This clearance dimension will increase with
large diameter pipes. The environment should be free of corrosive liquids/fumes, temperature
extremes and heavy vibration. The following diagrams should be used as a guide to the proper
location for installing the meter.
3.1.1 General Site Selection Guidelines
GENERAL PRACTICES:
1. For best results, install the ow meter in a straight run of pipe, free of bends, tees,
valves, transitions and obstructions.
2. Straight run recommendations vary based on the nature of the upstream obstruction.
See the table below for guidelines in determining upstream straight run
recommendations based on the nature of the obstruction. Please note that depending
upon specic location details, more or less straight run may be required to produce a
satisfactory ow prole.
For 3” and larger pipe diameters
Obstruction on either side of meter
Straight run distance recommended
between meter and obstruction
Single bend preceded by ≥ 9 diameters of
straight pipe
10 Diameters
Pipe size reduction / expansion in straight
pipe run
10 Diameters
Single bend preceded by ≤ 9 diameters of
straight pipe
15 Diameters
Outowing tee / pump outow 20 Diameters
Multiple bends out of plane 30 Diameters
Inowing tee 30 Diameters
Control / modulating valve 30 Diameters